Palm Springs / West Valley Campus

“Promises are only kept when someone is watching.”

About Us: Past, Present and the Future

Promises Made Promises Happening, formerly Broken

For 20 years, voters in California’s Coachella Valley have been promised a full College of the Desert (COD) campus in Palm Springs, expanding from Palm Desert and Indio to all of the Coachella Valley. Two bond measures — Measure B in 2004 ($346 million) and Measure CC in 2016 ($577.8 million) — were sold to taxpayers on that explicit commitment. Land was acquired. Sites were chosen. Then the project stalled, paused, scaled back, and stalled again.

By 2021, COD’s new leadership had quietly succeeded in redirecting the remaining major portions of the bond funding to Indio, the City of Coachella, and Thermal, leaving the West Valley with its “temporary trailer campus footprint” for the distant future.

Students with West Valley Campus NOW signs
Students rally for the West Valley campus, November 2023.

In late 2021, Promises Made Promises Broken (PMPB) was formed by Coachella Valley residents who had voted for those bonds and refused to watch the commitments disappear. We are a non-partisan, nonprofit watchdog group dedicated to one thing: ensuring the long-promised Palm Springs campus was built.

Through public meetings, rallies, paid social media, sustained press coverage, and direct pressure on the Board of Trustees, PMPB and our partners helped put the Palm Springs campus back on track.

Curved steel framework on the Palm Springs campus corner
Corner of Tahquitz Canyon Way and Farrell Drive, April 2026.
Palm Springs campus construction site
Construction underway on the Palm Springs campus, April 2026.

Construction has resumed and reached a major milestone. PMPB remains committed to holding institutions accountable, ensuring voter-approved projects are prioritized appropriately, and seeing that the campuses promised by COD leadership are completed for the benefit of the entire Coachella Valley community.

Architectural rendering of the Palm Springs campus entrance at twilight
Architectural rendering — Palm Springs campus entrance. Opening Fall 2027!

What the rendering shows, voters will finally have. When the Palm Springs campus opens in Fall 2027, COD will be where it should have been a decade ago — anchored in the West Valley, accessible to the families and students who funded it. Promises Made Promises Happening.

PMPB’s next chapter is to help develop programming in hospitality, artificial intelligence, healthcare, and architecture.

“Promises are only kept when someone is watching.”

Palm Springs Campus — Timeline

YearKey Events
2004Measure B passes — $346 million bond
2010COD acquires 119.3 acres in North Palm Springs from the City for $1, with a covenant restricting use to college purposes
2014College Park Specific Plan adopted for Palm Springs; COD abandons it and pivots to buying the Palm Springs Mall
2016Measure CC passes — $577.8 million ($923.8 million total with Measure B); bond language explicitly promises West Valley campus
2017COD leases Palm Springs Unified School District (PSUSD) land for a temporary Palm Springs campus ($189K/yr for ~600 students)
2018
  • COD acquires the Palm Springs Mall property (at Tahquitz Canyon Way and Farrell Drive, just west of the airport) for $22 million
  • Bond Oversight Committee bylaws revised
2020
  • COD President Joel Kinnamon announces retirement (Dec)
  • Pandemic cited as the reason for pausing forward progress on the Palm Springs campus
2021
  • Martha Garcia appointed COD President (Jul)
  • Cathedral City shocked to learn Roadrunner Motors will be relocated (Oct)
  • Garcia backtracks on her claim that no feasibility study existed, after the Desert Sun finds a 2016 study on COD’s own website (Dec)
  • PMPB launches with full-page Desert Sun flyer (Dec 15)
2022
  • PMPB’s first Zoom attended by 175 participants (Feb)
  • Board of Trustees (BOT) votes to keep Roadrunner at the original Cathedral City site (Apr 22)
  • Joel Kinnamon defeats Aurora Wilson for BOT seat 54%–46% (Nov)
2023
  • Jan 19 — “COD Board to see new Palm Springs campus plans Friday” (Desert Sun). 152,000 sq ft proposed; no hotel in new plans.
  • Jan 20 — “COD Board delays vote on Palm Springs campus designs; Kinnamon seeks to censure Perez” (Desert Sun). Vote postponed (Trustee Jandt absent); Kinnamon files censure complaint against Trustee Perez.
  • March BOT meeting cancelled by Trustees Ruben Perez and Bea Gonzalez for lack of quorum, paralyzing campus progress
  • Apr 7 — COD President Martha Garcia announces her departure to lead Mt. San Antonio College
2024
  • Oct 29 — Palm Springs and COD reach agreement ending the 2-year dispute, reaffirming the Palm Springs campus
  • Nov 14 — Groundbreaking on the Palm Springs campus — 20 years in the making — with Palm Springs Mayor Jeffrey Bernstein
2025
  • May 20 — Acting Superintendent/President Val Martinez Garcia announces the West Valley Campus is “no longer a question of \’if,\’ but \’when\'”
  • Jun 12 — “COD construction closes most of the Palm Springs Cultural Center parking lot” (Desert Sun). 28-acre campus, ~$405M.
  • Nov 10 — “COD Palm Springs Campus Has Gone Vertical” — structural framing rises on the site
2026
  • Mar 30 — COD announces a major construction milestone for the Palm Springs campus
  • May 4 — “COD plans four-year casino management degree, but Cal State objects” (Desert Sun). Bachelor’s in casino & integrated resort management proposed; first cohort fall 2027 to align with PS campus opening.

Much of the Palm Springs campus reporting cited above was the work of Jonathan Horwitz, Desert Sun education reporter (Aug 2021 – Jun 2024), now with the Orange County Register.

Roadrunner Motors

“Promises are only kept when someone is watching.”

About Roadrunner Motors: Past, Present and the Future

Promises Made Promises Happening, formerly Broken

Roadrunner Motors is the automotive training facility College of the Desert (COD) committed to build in Cathedral City, funded by the same voter-approved bond measures — Measure B in 2004 ($346 million) and Measure CC in 2016 ($577.8 million) — that promised the Palm Springs campus. The site selected was the Ecoplex property at the corner of Murphy Way and East Palm Canyon Drive, in the heart of Cathedral City’s dealership and automotive service corridor. It was the right program in the right place.

In October 2021, COD’s new leadership abruptly announced the project would be relocated, citing a claimed 70% cost overrun at the original site. An internal March 2021 memo from Dr. Annebelle Nery to Mac McGinnis — never made public until April 2022 — pegged the actual overrun closer to 20%. Cathedral City residents, business owners, and elected officials were blindsided.

In late 2021, Promises Made Promises Broken (PMPB) was formed by Coachella Valley residents who had voted for those bonds and refused to watch the commitments disappear. We are a non-partisan, nonprofit watchdog group dedicated to ensuring voter-approved projects get built where they were promised — including the Roadrunner Motors program in Cathedral City.

Through public meetings, rallies, paid social media, sustained press coverage, and direct pressure on the Board of Trustees (BOT), PMPB and our partners brought the relocation decision under sustained scrutiny.

Roadrunner Motors site in Cathedral City
The Roadrunner Motors site in Cathedral City — the original Ecoplex property at the foot of the mountains.

On April 22, 2022, after months of advocacy, the BOT voted 5–0 to keep Roadrunner Motors at the original Ecoplex site in Cathedral City. The bond funding stayed where voters had directed it. The price tag was updated to $37.4 million in May 2022, and design work resumed.

Roadrunner Motors construction site
Roadrunner Motors under construction in Cathedral City, 2026.

What Cathedral City was promised, Cathedral City will get. Roadrunner Motors will deliver hands-on automotive training using a dedicated fleet of vehicles and current diagnostic, repair, and maintenance tools. Students will learn alongside the dense network of dealerships, repair shops, body specialists, and parts suppliers that surrounds the campus — with local employers mentoring, sharing expertise, and partnering on real-world projects.

Architectural rendering of Roadrunner Motors
Architectural rendering — Roadrunner Motors. Opening Spring 2027!

It is the right program, in the right place, finally back on track. Promises Made Promises Happening.

CC Mayor Mark Carnevale: “We went through a whole lot of bumps, roadblocks and troubles. But it was real worth the wait to have this happen here.”

Roadrunner Motors — Timeline

YearKey Events
2004Measure B passes — $346 million bond
2016Measure CC passes — $577.8 million; bond language includes the Cathedral City automotive training facility
2021
  • Mar 1 — Dr. Annebelle Nery memo to Mac McGinnis pegs Roadrunner cost overrun at 20% (withheld from the public until April 2022)
  • Aug 20 — First mention at the BOT of Murphy Way site issues for Roadrunner
  • Oct 28 — Cathedral City residents shocked to learn COD plans to relocate the automotive center, citing a claimed 70% cost overrun
  • Dec 17 — BOT meeting confirms Roadrunner is $13M over the original $23M budget (56%, not the 70% touted publicly)
2022
  • Apr 1 — BOT Study Session reviews site alternatives
  • Apr 2 — KESQ: BOT Chair Ruben Perez promises Roadrunner Motors will remain in Cathedral City
  • Apr 6 — Special BOT session in Cathedral City; the withheld March 2021 cost-overrun memo surfaces publicly
  • Apr 22 — BOT votes 5–0 to develop Roadrunner Motors at the original Ecoplex site in Cathedral City
  • May 19–20 — Updated price tag announced: $37.4 million
2024Oct 16 — “College of the Desert’s automotive training center breaks ground” (Desert Sun). 25,983 sq ft. CC Mayor Mark Carnevale: “We went through a whole lot of bumps, roadblocks and troubles. But it was real worth the wait to have this happen here.”
2025Nov 3 — “Roadrunner Motors Slated for Spring 2027 Opening” (Uken Report). 26,020 sq ft. Opening slipped from 2026 to Spring 2027; COD’s Scott Adkins: “back solidly on track.”

2023–2026 progress to be added.